Passage
Directions: Read the following information and answer the given question. A, B, C and D are working in a team to complete a project in 5 days. A and B together can complete the work in 10 days, C alone can complete the work in 15 days and A and D together can complete the work in 20 days.
If only A has to complete the whole work, then in how many days will he complete the project?