Multiple choice technology packaged enterprise solutions

Which two events take place when an invoice is matched to a purchase order (PO)? A. Tolerances are enforced. B. PO quantity billed is updated. C. PO quantity received is updated D. PO accounting information is copied over.

  1. A. A, B

  2. B. B, D

  3. C. B, C

  4. D. A, D

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

During PO matching, the system updates the quantity billed on the purchase order and copies PO distributions to create invoice distributions. Tolerances are checked (not 'enforced' in a way that blocks matching outright without settings), and quantity received is updated during receiving, not matching.