A company is constructing a bridge, and they estimate that it will take 60 days to complete the project. Initially, they assign 150 workers to the task, and after 45 days, they decide to hire an additional 100 workers and the work was finished on time as estimated. If they had not hired the additional workers, how many days behind schedule would the project be finished?