10 மனிதர்களால் 8 நாட்களில் கட்டிமுடிக்க கூடிய ஒரு கட்டுமான பணியை அரை நாளில் முடிக்க எத்தனை மனிதர்கள் வேண்டும்? 10 men can complete the construction work in 8 days. How many men do you need to complete the same task in half a day?

  1. 80

  2. 100

  3. 120

  4. 160

  5. இவற்றில் ஏதுமில்லை/None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

This is an inverse proportion problem. M1 * D1 = M2 * D2. 10 * 8 = M2 * 0.5. 80 = 0.5 * M2. M2 = 160.

AI explanation

By applying the formula M1D1 = M2D2 for constant work, we have M1 = 10 men, D1 = 8 days, and D2 = 0.5 days. Substituting these values gives 10 * 8 = M2 * 0.5, which simplifies to 80 = 0.5M2. Solving for M2 yields 160, meaning 160 men are needed to complete the construction work in half a day. The result is 160.