A can complete a task in 24 days and B can complete the same task in 30 days. They started working on the task together and C joined after few days. They all completed the project in 10 days. They got an amount of Rs. 2,000 for completing the project, what is C's share in the amount?

  1. Rs. 400

  2. Rs. 500

  3. Rs. 600

  4. Rs. 700

  5. Rs. 800