Which level of "people CMM" considers below areas: Workforce Planning, Competency Development and Knowledge and Skill Analysis. (Tie Breaker)

  1. Level 3 - Defined

  2. Level 4 - Predictable

  3. Level 2 - Managed

  4. Level 1 - Initial

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

People CMM Level 3 (Defined) focuses on establishing standard processes for workforce activities. Key areas at this level include Workforce Planning, Competency Development, and Knowledge and Skills Analysis. Level 2 (Managed) addresses basic practices, Level 4 (Predictable) adds quantitative management, and Level 1 (Initial) is ad-hoc.