In a Utility, how do I set a Status that can be tested in the flow?

  1. Use a Java step

  2. Call History-Add

  3. Use the TaskStatus-Add method

  4. Use a Transition

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

In Pega utilities, the TaskStatus-Add method is used to set a status value that can be tested later in the flow using Decision shapes. Java steps and Transitions don't set flow-testable statuses, and History-Add is for audit trail purposes, not flow control.