8 women cam complete a work in 10 days and 10 children take 16 days to complete the same work. How many days will 10 women and 12 children take to complete the work ?
Reveal answer
Fill a bubble to check yourself
8 women cam complete a work in 10 days and 10 children take 16 days to complete the same work. How many days will 10 women and 12 children take to complete the work ?