$12$ men complete a work in $9$ days. After they have worked for $6$ days, $6$ more men join them. How many days will they take to complete the remaining work ?
Reveal answer
Fill a bubble to check yourself
$12$ men complete a work in $9$ days. After they have worked for $6$ days, $6$ more men join them. How many days will they take to complete the remaining work ?