If 450 men can finish construction of an apartment in 20 days, then how many men are needed to complete the same work in 30 days?
Reveal answer
Fill a bubble to check yourself
If 450 men can finish construction of an apartment in 20 days, then how many men are needed to complete the same work in 30 days?