Multiple choice

36 labourers complete a work in 14 days. If work is to be completed in 8 days, then how many additional labourers are needed?

  1. 29

  2. 33

  3. 27

  4. 23

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation