Five women can do a work in 36 days. If the ratio of the capacity of a man to that of a woman is 3 : 1, then how many days will it take for 5 men to complete the same work?

  1. 12 days

  2. 15 days

  3. 18 days

  4. 108 days

  5. na

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

5 women take 36 days, so 1 woman takes 180 days. Since 1 man is as efficient as 3 women, 1 man takes 180/3 = 60 days. 5 men take 60/5 = 12 days.

AI explanation

The total work is 180 woman-days (5 x 36). Because a man has three times the capacity of a woman, 5 men equal the capacity of 15 women. The time required for 5 men to finish the work is 180 / 15, which equals 12 days.