When is the availability check triggered for capital expenditure project in Kraft APAC?

  1. Exceeds 20% of budget value

  2. Exceeds 15% of budget value

  3. 90% of budge value

  4. None of the above

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

In the Kraft APAC SAP system, the budget tolerance limit triggers the availability check when commitments exceed the budget by 15% (reaching 115% consumption). This threshold warns users or blocks transactions to prevent uncontrolled overspending. The 20% limit or 90% consumption settings do not match the system design.