Let the total work be 1 unit, with the combined daily work of 25 men and 15 women being 1/12. In 8 days, the group completes 8/12 or 2/3 of the work, leaving 1/3 of the work for the 25 men to finish in 6 days. This means 25 men complete 1/18 of the work per day, so their contribution to the original combined daily rate is 1/18. Subtracting this from the combined rate of 1/12 leaves 1/36, which represents the daily work of the 15 women. Since 15 women complete 1/36 of the work per day, they will finish the entire job in 36 days.