An engineer has completed 100 yards of a certain work in 24 days, with 5 men. How many men must he employ to finish the same work in 15 days?

  1. 8

  2. 10

  3. 12

  4. 6

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Using the formula M1*D1/W1 = M2*D2/W2, where W is constant: 5 * 24 = M2 * 15. M2 = 120 / 15 = 8.