Process of putting demand on a system and measuring its response is

  1. volume testing

  2. Stress testing

  3. Load testing

  4. Performance testing

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Load testing is the process of applying demand to a system and measuring its response under expected or normal conditions. Volume testing focuses on data volume, stress testing pushes beyond capacity, and performance testing is the broader category.