Multiple choice technology security

In the ASAP process what is the main activity carried out in the requirement analysis phase?

  1. Capture the customer requirements

  2. Update the project plan

  3. Capture and update the URS and SRS with security requirements for the project

  4. None of the above

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

In the ASAP requirement analysis phase, the key activity is capturing security requirements and documenting them in the URS (User Requirements Specification) and SRS (Software Requirements Specification) documents (C). Simply capturing customer requirements (A) isn't enough - they must be specifically security-focused. Updating project plans (B) is a secondary activity.