The phases of Test management with Quality Center in order are:
-
Specify Requirements, Specify Releases, Plan Tests, Execute Tests, Track Defects
-
Specify Requirements, Plan Tests, Specify Releases, Execute Tests, Track Defects
-
Specify Releases, Specify Requirements, Plan Tests, Track Defects, Execute Tests
-
Specify Releases, Specify Requirements, Plan Tests, Execute Tests, Track Defects
The correct Test Management process in Quality Center is: 1) Specify Releases (define release cycles), 2) Specify Requirements (define what to test), 3) Plan Tests (design test cases), 4) Execute Tests (run the tests), 5) Track Defects (manage bugs found). Requirements must come before test planning, and releases provide the timeline framework.
To answer this question, let's go through each option to understand why it is correct or incorrect:
Option A) Specify Requirements, Specify Releases, Plan Tests, Execute Tests, Track Defects - This option is incorrect because the order of phases is not correct. The "Plan Tests" phase should come after "Specify Requirements" and "Specify Releases".
Option B) Specify Requirements, Plan Tests, Specify Releases, Execute Tests, Track Defects - This option is also incorrect because the order of phases is not correct. The "Specify Releases" phase should come before "Plan Tests".
Option C) Specify Releases, Specify Requirements, Plan Tests, Track Defects, Execute Tests - This option is incorrect because the order of phases is not correct. The "Track Defects" phase should come after "Execute Tests".
Option D) Specify Releases, Specify Requirements, Plan Tests, Execute Tests, Track Defects - This option is correct because it follows the correct order of phases in Test management with Quality Center. The phases are:
- Specify Releases
- Specify Requirements
- Plan Tests
- Execute Tests
- Track Defects
The correct answer is Option D. This option is correct because it follows the correct order of phases in Test management with Quality Center.