Multiple choice technology testing

You want to view the child requirements data related to the tests that the requirements cover. Which graph type should you use to accomplish this?

  1. Progress graph

  2. Trend graph

  3. Requirements coverage graph

  4. Summary graph

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

The Summary graph in Quality Center provides a comprehensive view that includes child requirements and their relationship to tests. It shows hierarchical requirement data and which tests cover which requirements. Option A (Progress graph) tracks test execution progress over time. Option B (Trend graph) shows historical trends in testing metrics. Option C (Requirements coverage graph) focuses on coverage percentages rather than the hierarchical child requirement relationships.