Multiple choice technology testing

What are the various deliverables for OAT?

  1. Consolidated OA Checks OAT Plan OAT Strategy OAT Results Closure Report

  2. OAT Strategy WBS OAT Plan OAT Results Closure Report

  3. OAT Strategy Consolidated OA Checks OAT Plan OAT Results Closure Report

  4. WBS OAT Strategy OAT Results Waiver Report Closure Report

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

The complete OAT deliverable set includes: OAT Strategy (high-level approach), Consolidated OA Checks (verification criteria), OAT Plan (detailed test plan), OAT Results (test outcomes), and Closure Report (sign-off). Options A and B are missing key elements, and Option D incorrectly includes WBS and Waiver Report instead of required deliverables.