What type of review requires formal entry and exit criteria, including metrics:

  1. management review

  2. walkthrough

  3. inspection

  4. post project review

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Inspection is the most formal review type, characterized by peer examination, defined entry/exit criteria, formal roles, and collection of metrics. Walkthroughs and management reviews are less formal and lack strict entry/exit metrics.