Multiple choice technology programming languages

What are the two workbooks introduced when you use the Agile process template?

  1. Sprint and Iteration backlog

  2. Product and Iteration backlog

  3. Product and Sprint backlog

  4. None of the above

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

The Agile process template in TFS 2010 includes two key Excel workbooks: Product Backlog (for capturing and prioritizing all user stories/features for the product) and Iteration Backlog (for planning work in specific iterations). Sprint backlog is a Scrum term - TFS Agile uses 'iteration' instead of 'sprint'.