Prioritised list of requirements in a SCRUM project is called

  1. Project log

  2. Product backlog

  3. Sprint backlog

  4. Business requirements document

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

In SCRUM, the product backlog is the master list of all desired features, requirements, and work items. It is prioritized by the Product Owner and serves as the single source of truth for what needs to be built. The Sprint backlog is a subset selected for a specific sprint, while a Project log and Business requirements document are not SCRUM artifacts.