Multiple choice technology testing

In a risk-based approach the risks identified may be used to : i. Determine the test technique to be employed ii. Determine the extent of testing to be carried out iii. Prioritize testing in an attempt to find critical defects as early as possible. iv. Determine the cost of the project

  1. . ii is True; i, iii, iv & v are False

  2. i,ii,iii are true and iv is false

  3. ii & iii are True; i, iv are False

  4. ii, iii & iv are True; i is false

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

In risk-based testing, identified risks directly inform: (i) the selection of appropriate test techniques based on risk type, (ii) the depth and extent of testing allocated to high-risk areas, and (iii) prioritization to uncover critical defects early. However, (iv) project cost determination is a project management function outside the testing scope, making it the only false statement.