Multiple choice technology testing

Which of the following is not a major task of Exit criteria?

  1. Checking test logs against the exit criteria specified in test planning.

  2. Logging the outcome of test execution.

  3. Assessing if more tests are needed.

  4. Writing a test summary report for stakeholders

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Exit criteria evaluation involves checking logs, assessing if more tests are needed, and writing reports. Logging the outcomes of test execution is part of the Test Execution phase, not a task of evaluating or executing the Exit criteria phase itself.