When do you raise requirement defect?
-
Before FPQ
-
After FPQ
-
Before HLE
-
After HLE
B
Correct answer
Explanation
Requirement defects are raised after FPQ (likely Final Product Qualification or Formal Product Qualification). Before FPQ, requirements are still being clarified and finalized; raising defects during this stage would be premature as the requirements themselves may change. After FPQ, requirements are baselined, and any deviations from agreed requirements become legitimate defects. HLE (likely Higher Level Examination or High-Level Engineering) typically occurs earlier in the lifecycle.