The inputs for developing a test plan are taken from :

  1. Project plan

  2. Business plan

  3. Support plan

  4. None of the above

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

The test plan is primarily derived from the project plan, which contains scope, schedule, resources, and risk information needed for test planning. Business plans focus on financial/projection aspects. Support plans are for maintenance. The project plan provides the foundational information for developing an appropriate test strategy.