Multiple choice six-sigma green-belt

Which one of the following is not carried out in Improve?

  1. Generation of solutions

  2. Testing of solution

  3. Handover to process owner

  4. Selection of solutions

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

The Improve phase in DMAIC focuses on generating, selecting, and testing solutions. Handover to process owner occurs during the Control phase, which is the final phase after Improve. The Control phase ensures the improved process is documented, monitored, and sustained by the process owner. Therefore, handover is not carried out during Improve - it happens in the subsequent Control phase.