Multiple choice technology enterprise content management

Which of the following is true for a delivery ( choose four )

  1. A delivery line can be split.

  2. Delivery lines can be unassigned from a delivery

  3. Delivery lines can be assigned to a delivery before the pick release

  4. Qualifying delivery lines can be assigned to an existing delivery.

  5. Delivery lines can be assigned to deliveries only after pick release

  6. Delivery lines that have been shipped and interfaced can be invoiced.

Reveal answer Fill a bubble to check yourself
A,B,D,F Correct answer
Explanation

Delivery lines can be assigned to a delivery before pick release. The four correct options state that lines can be split, unassigned, assigned to existing deliveries if qualifying, and invoiced after being shipped and interfaced. The options asserting that lines can be assigned only after pick release or cannot be assigned before pick release are incorrect.