What are key areas of risk that have NO significant influence on a project :

  1. Project Size

  2. Experience & Technology

  3. Project structure, including internal and external project dependencies from other projects or areas.

  4. Profitability of the project in live

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Project profitability after delivery does not affect the project's development risk profile. Size, technology experience, and project structure with dependencies directly influence technical and schedule risk during development.