Multiple choice six-sigma green-belt

RPN in FMEA means

  1. Risk Preference Number

  2. Risk Probability Number

  3. Risk Priority Number

  4. Reliability Preference Number

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Risk Priority Number in FMEA is calculated by multiplying three ratings: Severity (how bad), Occurrence (how often), and Detection (how likely to find it). RPN ranges from 1 to 1000, with higher numbers indicating greater risk requiring priority attention.