Multiple choice technology testing

Final Inspection is performed by

  1. QAG

  2. Within the Project

  3. Outside the Project

  4. Both (a) and (b)

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Final Inspection (FI) is performed by the Quality Assurance Group (QAG), which is independent of the project team. This independence ensures objective assessment - it's not done by the project team itself (Within the Project) or entities outside the project (Outside the Project) in general terms.