Changes to the FRD after it is baseline are done through

  1. Project Change Request

  2. Project Clear Request

  3. Performance Change Registration

  4. Performance Clear Request

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Once an FRD (Functional Requirements Document) is baselined, it becomes a controlled document. Any modifications require a formal change control process to maintain traceability and ensure all stakeholders review and approve changes. Project Change Request is the standard mechanism for this.