Review the FRD and check for completeness and correctness of the document in terms of scope, requirements are done in

  1. Exit

  2. Validate

  3. Entry

  4. Task

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Under the ETVX (Entry, Task, Verification, Exit) process model, the actual action of reviewing the Functional Requirements Document (FRD) for completeness and correctness is classified as a Task. Entry criteria define prerequisites, Validation/Verification tests the output quality, and Exit criteria determine completion, making Task the correct phase.