Multiple choice technology testing

In which Order, QA testing process is performed

  1. System Integration ? QA ? Performance ? User acceptance ? Operational Readiness

  2. QA ? Performance ? System Integration ? User acceptance ? Operational Readiness

  3. QA ? System Integration ? User acceptance ? Operational Readiness ? Performance

  4. Performance ? User acceptance ? Operational Readiness ? System Integration ? QA

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

The correct QA testing sequence is System Integration Testing (SIT) → QA → Performance Testing → User Acceptance Testing (UAT) → Operational Readiness. This order ensures systems are integrated before functional QA, performance is validated after functional correctness, and user acceptance precedes operational readiness.