Work items created during PSU (Project Start Up) phase doesn’t include

  1. Induction Manual

  2. Project Plan

  3. Work Order

  4. Process Improvemtn Proposal

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

During Project Start Up (PSU), standard deliverables include the Project Plan, Work Order, and Induction Manual. Process Improvement Proposal is typically a post-project or ongoing improvement activity, not a PSU deliverable. PSU focuses on initial project setup and documentation.