Multiple choice technology

How is the schedule line determined?

  1. MRP type and item category group

  2. MRP Type and shipping point

  3. Item category and document type

  4. Item category and MRP type on the material master record

  5. Item category group and strategy group on the material master record

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

The schedule line category in SAP is determined by the item category group from the material master and the MRP type also from the material master record. These two fields control scheduling behavior through the schedule line category determination table. Document types, shipping points, and strategy groups influence other aspects but not the direct determination of schedule line categories.