Multiple choice technology testing

In Scrum, sprint lasts no more than

  1. 10 days

  2. 20 days

  3. 30 Days

  4. 60 Days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Scrum defines a sprint as a maximum 30-day (1 calendar month) iteration. Modern practice uses shorter 2-week sprints, but the formal Scrum Guide caps it at 30 days.