If 12 men can finish a work in 20 days, then in how many days 15 men will complete that work?
Reveal answer
Fill a bubble to check yourself
If 12 men can finish a work in 20 days, then in how many days 15 men will complete that work?
22
18
16
None of these
This is an inverse proportion problem: more men means fewer days. Total work = 12 men × 20 days = 240 man-days. With 15 men: 240/15 = 16 days. Option C is correct.
To solve this problem, we can use the concept of man-days of work.
Given that 12 men can finish the work in 20 days, we can calculate the total man-days required to complete the work.
Man-days = (Number of men) x (Number of days) = 12 x 20 = 240
Now, we need to find out how many days it will take for 15 men to complete the work.
Number of days = (Total man-days) / (Number of men) = 240 / 15 = 16
Therefore, 15 men will complete the work in 16 days.
The correct answer is C) 16.