Multiple choice technology

In a Sequence - Job activity, you are selecting a Multiple instance job and what happens if the Invocation ID is left blank?

  1. Invocation ID will not appear in Job activity

  2. Log will appear in the original job name

  3. You cannot leave it blank

  4. None of the above

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

When configuring a multiple instance job in a DataStage sequence, the Invocation ID is a mandatory parameter that uniquely identifies which instance to invoke. The interface enforces this requirement and will not allow the field to remain blank.