Multiple choice technology

Which stage in Job Sequence is used to run two parallel jobs in parallel?

  1. Job Activity

  2. Routine Activity

  3. Sequencer

  4. User Variables Activity

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

The Sequencer activity in DataStage Job Sequences is specifically designed to trigger multiple activities in parallel. It can wait for multiple triggers to complete and then launch subsequent activities simultaneously.