To Ensure that the Quality Center can Run Tests in QTP, what setting must be set first in QTP?

  1. Allow QC to run tests remotely

  2. Enable QC Integration

  3. Allow other Products to control QTP

  4. Allow other Products to run tests remotely

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

To enable Quality Center to execute QTP tests remotely, you must configure QTP to allow remote test execution by setting the 'Allow QC to run tests remotely' option. This permission must be enabled in QTP before Quality Center can control test execution.