What of the following is not a sequential processing?

  1. Using a series of GN calls followed by a GNP call
  2. Using unqualified SSA's with GNP
  3. Using qualified SSA's with GU
  4. Using qualified SSA's with GN
  5. Using no SSA's with GNP