QuestionClick to flip
Changes to the FRD after it is baseline are done through
AnswerClick to flip back
A
Project Change Request
💡 Explanation:
Once an FRD (Functional Requirements Document) is baselined, it becomes a controlled document. Any modifications require a formal change control process to maintain traceability and ensure all stakeholders review and approve changes. Project Change Request is the standard mechanism for this.