0

testing Online Quiz - 43

Description: testing Online Quiz - 43
Number of Questions: 20
Created by:
Tags: testing
Attempted 0/20 Correct 0 Score 0

Load Testing Tools

  1. reduces the time spent by the testers

  2. reduces the resources spent (hardware)

  3. mostly used in web testing

  4. all of the above


Correct Option: D

Reviews, static analysis and dynamic testing have the same objective –

  1. identifying defects.

  2. fixing defects.

  3. 1 and 2

  4. None


Correct Option: A
Explanation:

To solve this question, the user needs to know about the objectives of reviews, static analysis, and dynamic testing.

Reviews, static analysis, and dynamic testing have the same objective of identifying defects.

Option A is the correct answer.

Option B is incorrect because fixing defects is not the objective of reviews, static analysis, and dynamic testing. Their objective is to identify defects so that they can be reported for fixing.

Option C is incorrect because the statement "1 and 2" is not clear. It is not clear what "2" is referring to, and it is unclear how it is related to the objective of identifying defects.

Option D is incorrect because, as mentioned earlier, the objective of reviews, static analysis, and dynamic testing is to identify defects. Therefore, the statement "None" is incorrect.

The Answer is: A

Defect arrival rate curve:

  1. Shows the number of newly discovered defects per unit time

  2. Shows the number of open defects per unit time.

  3. Shows the cumulative total number of defects found up to this time.

  4. Any of these, depending on the company.


Correct Option: A

AI Explanation

To answer this question, you need to understand the concept of a defect arrival rate curve.

A defect arrival rate curve shows the number of newly discovered defects per unit time. It represents the rate at which defects are being identified or reported during a specific period.

Option A) Shows the number of newly discovered defects per unit time - This option is correct. As mentioned above, a defect arrival rate curve represents the number of newly discovered defects per unit time.

Option B) Shows the number of open defects per unit time - This option is incorrect. The defect arrival rate curve does not represent the number of open defects. It only represents the rate at which new defects are being discovered.

Option C) Shows the cumulative total number of defects found up to this time - This option is incorrect. The defect arrival rate curve does not show the cumulative total number of defects found. It only shows the rate at which new defects are being discovered.

Option D) Any of these, depending on the company - This option is incorrect. The defect arrival rate curve is specifically used to represent the number of newly discovered defects per unit time and is not dependent on the company.

Therefore, the correct answer is A) Shows the number of newly discovered defects per unit time. This option is correct because the defect arrival rate curve represents the rate at which new defects are being identified or reported.

  1. The probability the negative event will occur

  2. The potential loss or impact associated with the event

  3. Both a and b

  4. Neither a nor b


Correct Option: C

We can achieve complete statement coverage but still miss bugs because:

  1. The failure occurs only if you reach a statement taking the TRUE branch of an IF statement, and you got to the statement with a test that passed through the FALSE branch.

  2. The failure depends on the program's inability to handle specific data values, rather than on the program's flow of control.

  3. Both A and B

  4. We are not required to test code that customers are unlikely to execute.


Correct Option: C

Who is responsible for conducting test readiness review?

  1. Test manager

  2. Test engineer

  3. both A & B

  4. Project Manager


Correct Option: A

What if the project isn't big enough to justify extensive testing?

  1. Use risk based analysis to find out which areas need to be tested

  2. Use automation tool for testing

  3. a and b

  4. None of the above


Correct Option: A
  1. A. Scheduling test analysis and design tasks.

  2. B. Initiating corrective actions.

  3. C. Monitoring progress and test coverage.

  4. D. Measuring and analyzing results.


Correct Option: A
Explanation:

To answer this question, the user needs to know the basic tasks and objectives of test planning.

The correct answer is:

A. Scheduling test analysis and design tasks.

Explanation:

Test planning is a critical phase of the software testing life cycle. It involves defining the approach, objectives, and scope of testing, as well as identifying the necessary resources, tools, and techniques to achieve the desired results.

A major task of test planning is scheduling test analysis and design tasks. This involves determining the testing activities that need to be performed, allocating the necessary resources and time for each activity, and creating a timeline or schedule for completing the tasks. This ensures that the testing process is systematic, organized, and efficient.

Initiating corrective actions, monitoring progress and test coverage, and measuring and analyzing results are important tasks in software testing, but they are not the major tasks of test planning. These tasks are typically performed during the testing execution and evaluation phases.

Therefore, option A is the correct answer.

Where may functional testing be performed?

  1. A. At system and acceptance testing levels only.

  2. B. At all test levels.

  3. C. At all levels above integration testing.

  4. D. At the acceptance testing level only.


Correct Option: B
  1. A. To identify potential application failures by use of a test specification.

  2. B. To identify defects in any software work product.

  3. C. To identify spelling mistakes in a requirements specification.

  4. D. To identify standards inconsistencies in the code.


Correct Option: B

Who would USUALLY perform debugging activities?

  1. A. Developers.

  2. B. Analysts.

  3. C. Testers.

  4. D. Incident Managers.


Correct Option: A

Which of the following is a MAJOR task of test planning?

  1. Scheduling test analysis and design tasks.

  2. Initiating corrective actions.

  3. Monitoring progress and test coverage.

  4. Measuring and analyzing results.


Correct Option: A

AI Explanation

To answer this question, you need to understand the major tasks involved in test planning. Let's go through each option to understand why it is correct or incorrect:

Option A) Scheduling test analysis and design tasks - This option is the correct answer. Scheduling test analysis and design tasks is a major task of test planning. It involves determining the timeline and sequence of activities related to analyzing the requirements, designing test cases, and creating test data.

Option B) Initiating corrective actions - This option is not a major task of test planning. While corrective actions may be necessary during the testing phase, they are not directly related to the planning stage.

Option C) Monitoring progress and test coverage - This option is not a major task of test planning. Monitoring progress and test coverage is typically part of the test execution and control phase, not the planning phase.

Option D) Measuring and analyzing results - This option is not a major task of test planning. Measuring and analyzing results are typically done during the test execution and evaluation phase, not during the planning phase.

The correct answer is A) Scheduling test analysis and design tasks. This option is correct because it accurately describes a major task involved in test planning.

Where may functional testing be performed?

  1. At system and acceptance testing levels only.

  2. At all test levels.

  3. At all levels above integration testing.

  4. At the acceptance testing level only.


Correct Option: B
  1. To identify potential application failures by use of a test specification.

  2. To identify defects in any software work product.

  3. To identify spelling mistakes in a requirements specification.

  4. To identify standards inconsistencies in the code.


Correct Option: B

Who would USUALLY perform debugging activities?

  1. Developers.

  2. Analysts.

  3. Testers.

  4. Incident Managers.


Correct Option: A

The object Respository Manager enables us to open ________shared object respositories and modify them as needed

  1. Multiple

  2. Two

  3. Three

  4. Seven


Correct Option: A
  1. Object Repositories dialog box

  2. Object Repositories Manager dialog box

  3. Associate Repositories Manager dialog box

  4. Associate Repositories dailog box


Correct Option: D
- Hide questions