0

testing Online Quiz - 43

Description: testing Online Quiz - 43
Number of Questions: 20
Created by:
Tags: testing
Attempted 0/20 Correct 0 Score 0

Load Testing Tools

  1. reduces the time spent by the testers

  2. reduces the resources spent (hardware)

  3. mostly used in web testing

  4. all of the above


Correct Option: D

Reviews, static analysis and dynamic testing have the same objective –

  1. identifying defects.

  2. fixing defects.

  3. 1 and 2

  4. None


Correct Option: A
  1. Shows the number of newly discovered defects per unit time

  2. Shows the number of open defects per unit time.

  3. Shows the cumulative total number of defects found up to this time.

  4. Any of these, depending on the company.


Correct Option: A
  1. The probability the negative event will occur

  2. The potential loss or impact associated with the event

  3. Both a and b

  4. Neither a nor b


Correct Option: C

We can achieve complete statement coverage but still miss bugs because:

  1. The failure occurs only if you reach a statement taking the TRUE branch of an IF statement, and you got to the statement with a test that passed through the FALSE branch.

  2. The failure depends on the program's inability to handle specific data values, rather than on the program's flow of control.

  3. Both A and B

  4. We are not required to test code that customers are unlikely to execute.


Correct Option: C
  1. Test manager

  2. Test engineer

  3. both A & B

  4. Project Manager


Correct Option: A
  1. Use risk based analysis to find out which areas need to be tested

  2. Use automation tool for testing

  3. a and b

  4. None of the above


Correct Option: A
  1. A. Scheduling test analysis and design tasks.

  2. B. Initiating corrective actions.

  3. C. Monitoring progress and test coverage.

  4. D. Measuring and analyzing results.


Correct Option: A
  1. A. At system and acceptance testing levels only.

  2. B. At all test levels.

  3. C. At all levels above integration testing.

  4. D. At the acceptance testing level only.


Correct Option: B

What is the MAIN objective when reviewing a software deliverable?

  1. A. To identify potential application failures by use of a test specification.

  2. B. To identify defects in any software work product.

  3. C. To identify spelling mistakes in a requirements specification.

  4. D. To identify standards inconsistencies in the code.


Correct Option: B

Who would USUALLY perform debugging activities?

  1. A. Developers.

  2. B. Analysts.

  3. C. Testers.

  4. D. Incident Managers.


Correct Option: A

Which of the following is a MAJOR task of test planning?

  1. Scheduling test analysis and design tasks.

  2. Initiating corrective actions.

  3. Monitoring progress and test coverage.

  4. Measuring and analyzing results.


Correct Option: A
  1. At system and acceptance testing levels only.

  2. At all test levels.

  3. At all levels above integration testing.

  4. At the acceptance testing level only.


Correct Option: B

What is the MAIN objective when reviewing a software deliverable?

  1. To identify potential application failures by use of a test specification.

  2. To identify defects in any software work product.

  3. To identify spelling mistakes in a requirements specification.

  4. To identify standards inconsistencies in the code.


Correct Option: B
  1. Developers.

  2. Analysts.

  3. Testers.

  4. Incident Managers.


Correct Option: A

The object Respository Manager enables us to open ________shared object respositories and modify them as needed

  1. Multiple

  2. Two

  3. Three

  4. Seven


Correct Option: A
  1. Object Repositories dialog box

  2. Object Repositories Manager dialog box

  3. Associate Repositories Manager dialog box

  4. Associate Repositories dailog box


Correct Option: D
- Hide questions