The meeting conducted after the SPRINT to identify opportunities for improvement is called

AnswerClick to flip back
A
Sprint retrospective
💡 Explanation:

The Sprint retrospective is a dedicated meeting held after each sprint specifically to reflect on the team's process and identify improvements. The Sprint review demonstrates the working product, Sprint planning commits to the next sprint's work, and the daily standup is for status coordination.