Multiple choice

When contingency planning an ICT system at highest level, chosen solution should provide for

  1. minimal disruption for customers

  2. minimal disruption for office staff

  3. recovery of all financial data

  4. full business continuity

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Contingency planning at the highest level aims for business continuity, ensuring that the entire organization can continue to function despite a system failure. Other options are specific subsets of a broader continuity plan.