Multiple choice

The product structure of an assembly P is shown in the figure. Estimated demand for end product P is as follows

           
Week
1
2
3
4
5
6
Demand
1000
1000
1000
1000
1200
1200

Ignore lead times for assembly and sub-assembly. Production capacity (per week) for component R is the bottleneck operation. Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is

  1. 1000

  2. 1200

  3. 2200

  4. 2400

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

$\text{Hence, the smallest capacity that will ensure a feasible production plan up to week 6 is 2200}$