Multiple choice

The total number of decision variables in the objective function of an assignment problem of size n x n (n jobs and n machines) is

  1. n2

  2. 2n

  3. 2n – 1

  4. n

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Correct option is (1).

Keep practicing — related questions

  • For an LPP having " n " decision variables, there must be an equal number of constraints.
  • If there are m sources and n destinations in a transportation matrix, the total number of basic variables i...
  • Consider a linear programming problem with two variables and two constraints. The objective function is : M...
  • A Go-Back-N ARQ uses a window of size 7. How many bits are needed to define the sequence number?
  • If the input of the following program is 10, what will be the output? void print(int); void main() { int n;...
  • Which of the following statements about electromagnetic spectrum is/are not correct? (A) The velocity of X-...
  • The theory explaining that the ratio between the number of X-chromosomes and the number of complete sets of...
  • Which of the following functions is used to modify the size of previously allocated space?
Play the full quiz 🎤 Practise this topic out loud

Practice this topic

  • Optimization and Mathematical Programming (1582 questions)
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy