P is 20% more efficient than Q. P can complete a work in 24 days. If P and Q work together, how much time will it take to complete the same work?

  1. 10 days

  2. 11 days

  3. 14 days

  4. 15 days

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

P and Q together can do the work in = 144/11 = 14 days

Keep practicing — related questions

  • Directions: A sentence is given in four parts (P, Q, R, and S). One of the parts contains a grammatical err...
  • If a bacterial cell divides every minute, it takes 59 minutes to fill one half of the cup. How much time wo...
  • Directions: Choose the correct word/phrase to complete the given sentence. How ________ time does it take t...
  • Directions: Based on the information from the paragraph, choose the appropriate number 1 – 4 to complete th...
  • Which of the following statements are incorrect regarding Plasmodium vivax? P. Duration of exoerythrocytic ...
  • Directions: A sentence has been divided into four parts as P, Q, R and S. Rearrange the parts to form a mea...
  • Directions: A sentence has been divided into four parts as P, Q, R and S. Rearrange the parts to form a mea...
  • Directions: A sentence has been divided into four parts as P, Q, R and S. Rearrange the parts to form a mea...
Play the full quiz 🎤 Practise this topic out loud

Practice this chapter

  • Time and Work (2195 questions)
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy